印一座立交桥建了7年都没完工还塌了 真没谁了! – 铁血网
印一座立交桥建了7年都没完工还塌了 真没谁了!
依然是中国心 2016/4/1 20:13:43
Kolkata flyover: Political push, tech faultcould be crash cause
加尔各答立交桥:政治推动,技术缺陷也许是坍塌原因
KOLKATA: The inordinate delay in executingthe work and Mamata Banerjee’s subsequent rush to open the 2.2km Vivekananda Road flyover seem to be its undoing,literally.
The 2.2-km Vivekananda Road flyover, beingconstructed since 2009, has been beset by delays. Has the delay caused fatiguein execution? Amid perpetual postponement, in November last year, chiefminister Mamata Banerjee announced opening the flyover by February 2016, notcaring that 24% of the work was still left.
工程无节制的延迟,以及玛玛塔班纳吉随后急着开放2.2公里长的维韦卡南达路立交桥,似乎是祸根。
2.2公里长的维韦卡南达路立交桥从2009年开始修建,一直受拖延所困扰。是否是延期导致了施工疲劳?在无限期推迟后,去年11月,首席部长玛玛塔班纳吉宣布要在2016年2月份开放那座立交桥,全然不顾24%的工程有待完工。
With an eye on the assembly elections, thechief minister in November last year-at a Jagaddhatri Puja event-had declaredthe inauguration of the flyover by February 2016, ostensibly not paying muchthought to the fact that 24% of the work was left. Informed by her urbandevelopment minister Firhad Hakim that the deadline was implausible, sherelented to postpone the date but maintained that it should be finished bySeptember. As a result, immense pressure was apparently put on the implementingagency, KMDA, and builder IVRCL to meet the deadline, the 10th since theproject started in 2009.
考虑到议会选举就要来临,首席部长玛玛塔班纳吉去年11月宣布,要在2016年2月为这座立交桥举行完工典礼,全然不顾这样一个事实,即24%的工程还没完成。城市发展部长FirhadHakim表示这一截止期限是难以置信的,为此她同意推迟完工的日期,但是坚持要在9月份之前完工。结果,施工方受到了巨大压力。
After a little over six years, only 0.9km of the 2.2km flyover has been constructed, to add up to 59spans. It is the 60th span that was being cast which collapsed on Thursday. Thecasting was on for two days, but the work, carried out from Wednesday midnighttill 5am on Thursday, was faulty, engineers suspected. They said the 100m span, or the deck slab-cum-girder fortwo stands, could have given way due to a failure of a pier in between.
6年多来,2.2公里长的立交桥只修建了0.9公里,浇筑了59个桥段,正是第60个正在浇筑的桥段在3月31日坍塌了。浇筑持续了两天,从3月30日深夜持续到31日凌晨5点,但是工程师怀疑施工存在缺陷。他们称,跨度100米的桥段可能是桥墩不结实而坍塌的。
Though junior urban development ministerBabul Supriyo blamed the design, an engineer said: “It looks more like a constructionfailure. Some error might have occurred in the construction procedure ormaintaining the sequence.” IVRCL group head (HR and administration) K Panduranga Rao pointedout that the crash was caused by a missing girder. “One girdle missed leading to asecond one to fall off,” he said.
城市规划部长BabulSupriyo将其归咎于设计,一位工程师说:“看起来更像是施工失败。施工过程中也许出现一些失误。”IVRCL集团指出,立交桥坍塌是少了一根大梁导致的。
以下是《印度时报》读者的评论:
SpeakTruth
Contractor should be held responsible for this.Many innocent lives have been lost.
承包商要负责。
许多无辜生命因此失去
Delhi Man
Many a times its not the contractor, but thepolitical leadership which is responsible of putting unreasonable pressure andthus leading to accidents..
许多时候不是承包商的问题,而是政客们施加了巨大压力,导致事故的发生
mahendrakumar Nayak
Contractor and the technical persons are tobe blamed.
要怪就怪承包商和技术人员
Boforsthief
corruption is the primary cause of all suchfailures. We should introduce death penalty for corruption
腐败是此类事故的主因 印度应对腐败引入死刑的惩罚
DRCHINNA
She declared opening of flyover withoutconsulting technical team!! Politicians often make this mistake, the questionis why?
没有咨询技术团队,她就宣布立交桥的开放日期!政客们经常犯这类错误 为什么会这样?
AnandMirle
If it is a construction zone, how come allsorts of vehicle traffic were going under or in the vicinity of theconstruction area -Buses, trucks, private vehicles, hand pulled rikshaws, motorcycles….Didn’t they cardon off the constructionare and create a detour for all vehicle and pedestrian traffic – This is ridiculous constructionmanagement…..
既然是施工区域,为什么各种机动车辆会在下面经过,公交车啊,货车啊,私家车啊,人力车,摩托车之类的… 难道就没有把施工区域围起来吗,让各种车辆让道 施工管理太荒谬了
Captmithilesh Kumar
It is high time the Chief Minister should be madeaccountable for this tragedy. Let some file PIL to the highest Court.
首席部长要为这起悲剧接受问责
ankitsinha
Stupid Govt. officials and ConstructionCompany.. Playing with life of people…Jail them all
那些官员,还有建筑公司,玩弄人们的生命 全部投入监狱吧
Amita
I think there may have been pressure tofinish the work before elections and some shortcuts may have been taken
我认为,施工方为了赶在大选前完工而走了一些捷径
PKM
Mamtamai should have resigned on moralground. Enough of hypocrisy and double standards.
从道德层面上来看,玛玛塔应引咎辞职 受够了那种虚伪,受够了那种双重标准
Debasismondal Mondal
OMG an 18 months project took more than six years………
哦天啊,工期18个月的工程拖了6年多
Vsgr
For the politicians, this is a minorincident as none of the politicians or their relatives have died or injured inthis incident.
对政客们来说,这是小事故,毕竟他们没有亲戚在这起事故中伤亡
RamjiAbinashi
how can an entire girder be missing ? It is not anail or pin
怎么会少了一根大梁?那可不是螺丝钉,也不是大头针啊
PbchChowdhuri
If this flyover could not take the load ofthe cement topping, how can it take the load of the heavy Kolkata traffic.
如果承受不住桥段的重量,怎么能承受得住繁忙的交通呢
GirishKanagotagi
If a project takes seven years, the oldconcrete can not bind well with the new one
工程拖了7年,旧的混凝土和新的混泥土会结合不够紧密
SuchandaRay
Any construction site should be alwaysbarricaded, which is not followed in most of the cases. This is also a man madedisaster due to negligence.
施工场地必须围起来,而很多情况并未这样做 这是一起人为疏忽导致的灾难
rajkumarsarkar
dangerous political game
危险的政治游戏
本站仅提供存储服务,所有内容均由用户发布,如发现有害或侵权内容,请点击举报
打开APP,阅读全文并永久保存 查看更多类似文章
猜你喜欢
类似文章
【热】打开小程序,算一算2024你的财运
Deoghar Jharkhand - how to travel
驾驶员再培训系列之交通标志识别
南拓北延!人民路即将贯通南北外环,菏泽将启动建设万福河景观带!
京台高速公路跨京沪铁路路段改扩建方案研究
iPhone 5 Meta
印度艺术家华苏迪奥·盖同德的巅峰之作《无题》(Untitled,1990)
更多类似文章 >>
生活服务
热点新闻
分享 收藏 导长图 关注 下载文章
绑定账号成功
后续可登录账号畅享VIP特权!
如果VIP功能使用有故障,
可点击这里联系客服!

联系客服